Task Blog

As of 12/8/08

Visit this page to review and contribute to log of current project tasks.
Send changes, additions, updates, offers of help, questions, etc to Karen
(or call 253-4683 - leave message.)

CLICK HERE FOR WORD DOCUMENT
(Page is set for "Landscape")

Done

Task

“Facilitator(s)”

Assistants/
Contractors
 

Coordinate Davenport Theatrical 2/22/09 Production

Karen R.  
 

Coordinate Peter Davenport UFO Presentation

   
 

Coordinate Charlotte Schacher art workshops

   
  Install floor tile in bathrooms   Debra, Jimmy, Carol, Gale, Linda
  Install wall tile in bathrooms  
  Build & install bathroom partitions    
  Research & purchase handicapped chair lift    
  Install handicapped chair lift    
  Hang lobby fan    
  Hook up power to apartment lights    
  Run power circuits to both roof exhausts    
* Finish stair railings both sides (wall railing not done yet)    
  Finish trim under stairs    

Install angle stops in restrooms

 

 

Set toilets & urinals

 

 

Make and install Temporary restroom stalls

 

 

Find and install sinks

 

 

Install mirrors (Ladies Room - anyway)

 

 

Install overhead lites and vanity lites

 

 

Finish plumbing hook up in basement

 

 

Install water heater

 

 

Run circuit for womens room heater

 

 

Install wall heaters in restrooms

 

 

Hang chandeliers

 

 

Install stair sconce

 

 

Check on “rope lights” for stairs

 

 

Wire in lobby lights and fan

 

 

Find and install lobby door entry hardware

 

 

Clean brickwork in lobby

 

 

Paint sheet rock in lobby

 

 

Run 125 amp service to stage

 

 
Power circuits to furnaces above stage    
Install two 150,000 BTU furnaces above
auditorium (vendor)
   
Seal up west wall (roof) on stage